77 Questions customers ask when evaluating Octave Attune EAM

77 Questions customers ask when evaluating Octave Attune EAM

VisualK has been marketing, selling, implementing and supporting Octave Attune EAM since 2007. In all those years I think we have heard every question prospects and customers ask when they are evaluating Octave Attune EAM (obviously exaggerating here). So, we sat down and wrote as many questions as we could remember and decided that we could post it our blog for those of you out there thinking if Octave Attune EAM is the right solution for your business.

However, you just don’t buy a piece of software, you buy a complete solution which includes software and consulting services to make it work for you. The following 77 questions include information about HxGN, VisualK, Contracts and Implementation.

Who is HxGN?

Hexagon is a global leader in digital reality solutions. Combining sensor, software and autonomous technologies. They are putting data to work to boost efficiency, productivity, quality and safety across industrial and mobility applications. Technologies are shaping production and people related ecosystems to become increasingly connected and autonomous – ensuring a scalable, sustainable future.

Hexagon is located in Estocolmo, Suecia and then offices across the planet.

Who is VisualK?

Since 1997, VisualK has been committed to add value to its customers through the implementation of processes, software and technology to solve their needs. A gold channel partner with Octave Attune EAM Global Solutions, VisualK is focused in its Enterprise Asset Management (EAM) practice. Our portfolio of asset management and maintenance customers includes electric power generators, fleet operators, manufacturers and facilities managers. VisualK has offices in Atlanta, Georgia, San Juan, Puerto Rico, Guatemala and El Salvador. We are not allowed to say that we are the best partner in the galaxy.

What is a channel partner?

As a channel partner, we market, sell, implement and support some of HxGN’s product mostly in regions where HxGN does not have offices. Another important aspect is that when you decide to buy the software, you do not buy it from VisualK. You buy it from HxGN. VisualK acts as an intermediary and we receive a commission from HxGN on software sales.

How old is Octave Attune EAM?

How frequently does HxGN update Octave Attune EAM? The current encarnation of Octave Attune EAM has been around since 2000. But it has evolved from MP2 which has been (and still is) around since 1986. There is a major release annually.

Is there a roadmap?

Can we get a copy of the roadmap? There is a roadmap which is presented to customer. However, this roadmap is subject to change and it is for information only. This document is delivered to customers.

How should I evaluate Octave Attune EAM?

RFP? Requirements Matrix? A requirements matrix of some sort is probably the best starting point to conduct a thorough and serious evaluation. Depending of the scope, complexity and budget you may be required to conduct a formal Request for Proposal (RFP) process. One key consideration is the composition of the evaluation committee. It should be headed by Operations and Maintenance with the support of Information Technology (not the other way around, but that’s just me)

Can I just download a requirements matrix?

Thanks to the magic of the Internet and Google you can find almost everything, including a CMMS or Asset Management System requirements matrix. But please, don’t just copy and paste it. It should be a good start and the beginning of the conversation.

Can VisualK help in the evaluation process?

Our job is to help you understand your requirements and the best options available to fulfill them.

What are the functional areas that will benefit (or by impacted) by implementing EAM?

Maintenance, Engineering, Accounting, IT, Reliability, Inventory Management, Procurement and Operations

Do we need to involve our IT department/leadership in the selection and implementation process?

You should. If the software will be implemented on-premise, they must understand and determine what servers will be used, what database will be used and all the fun stuff that goes with it. If Octave Attune EAM will be implemented in the cloud (Software as a Service, or SaaS), they should still be involved.

What kind of contracts will be required for this kind of project?

Implementing Octave Attune EAM has two sides; licensing and services. You will execute the following contracts with HxGN; Software License Agreement (SLA) and Software Support Agreement (SSA), Order Form (OF) or a Subscription License and Services Agreement for Cloud deployments. You will execute the following contracts with VisualK; Consulting Services Agreement and Statement of Work.

What pre-work do we need to do before the implementation?

Clearly define your requirements and objectives for the project. Make sure all the parties involved or impacted are informed and committed.

What are the most common risks to be considered when implementing?

Most risks come from the unkowns. Sometimes we don’t know how good the data and how much effort will go into sorting, cleaning and loading data into the system. Other times we don’t know how good/bad the communications (network, internet access) are. Sometimes an integration partner is not fully engaged in the project. But our #1 enemy is not having management involvement and support.

How much would the implementation cost?

There is no set price. It depends on the modules, the number of users and the implementation scope. All of these are estimated initially and later validated after the design document has been approved.

How long does it take to implement EAM?

Depends. We have implemented combined-cycle power plants using our implementation accelerator in just 3 months.

What is the typical duration of the project?

A typical implementation of Octave Attune EAM usually takes 6 months, without an implementation accelerator.

How do you estimate how much does a project costs?

It based on the scope defined for the implementation. There are 2 main costs: licensing and, services. Licensing is determined by the number and types of users as well by any advanced module required. We estimate the services by defining an implementation plan which includes tasks (based on the scope), resources and time using Microsoft Project. The project consulting fees are calculated using the Microsoft Project cost estimation functionality.

What is time and material?

We report and tally the time spent per activity. The actual time by a resource times the resource hourly rate yields the actual consulting fees that are charged to a project/customer.

What is fixed-price?

Under a fixed-price agreement, the parties negotiate a lump sum for the execution of the project.

Which one is more convenient?

Which one is more fair? In our experience, a Time and Material engagement is more convenient because users are constantly aware of the importance of using everyone’s time in the best way possible. No never-ending meetings, no running around. It has been our best tool to keep everybody aligned. If we (that’s VisualK AND the customer) have done a good job defining requirements and scope and estimating there should be no surprises and the cost should be kept under control. Fairness is a function of risk.

What is the difference between On Premise (On-prem) and Software as a Service?

First and foremost, It is important to understand that it’s the same software with the same features either way. On-premise refers to installing the software in your server(s) and users connect to it through your network (do people still use the term intranet?). Contractually, you buy the perpetual license and then you pay a annual maintenance & support fee. Software as a Service is like a rent, which is paid annually.

What is perpetual licensing?

You own the software and you can use forever.

What is Annual Maintenance & Support?

This is a fee that entitles the customer with new releases and patches of the software (hence maintenance). It also entitles the customer to access the InforXtreme or Concierge system to create support tickets and receive assistance with said tickets when Octave Attune EAM misbehaves (hence support). However, VisualK provides 1st level support and then raises issues/bugs to HxGN for 2nd level support.

Why must we pay M&S before we begin to use the system in production?

Can’t we just start paying maintenance & support when go-live? You may be able to use Octave Attune EAM in production in a few days or weeks and you may require support during the implementation process.

Who will support our company once the implementation project has been completed?

This is where the Maintenance & Support program comes in so VisualK and HxGN will support you. VisualK offers the Advanced Assistance program which is based on a pre-defined block of hours for the year to conduct training, implement additional functionality and support.

What is a named user?

This is a type of licensing in which every user that is granted access to Octave Attune EAM is required a licensed.

What is a concurrent user?

Under this licensing, you can grant access to an unlimited number of users (names) but the number that can be connected to the system at any time is determined by the number of concurrent users licensed. It’s really a pool of users.

Which one should I use?

Named. HxGN does not license concurrent users anymore.

What modules do you offer?

A lot! The following diagram illustrates the available modules in Octave Attune EAM

What modules should I use (implement)?

It depends on your industry and circumstance. You must have assets, work management, metrics and reports. You should consider Inventory Management to control your spare parts inventory. You also have the option to procure parts and services from Octave Attune EAM. Few maintenance people sit at their desks all day, so you want to consider using the application on your mobile device (tablet or smartphone).

How would we know what to implement?

Let us guide you. We have the experience implementing Octave Attune EAM in your industry. We will suggest the functionality and processes that should be implemented and provide you with insights and best practices so you can make an informed decision.

Do I have to implement everything at once?

You do not. At a bare minimum set your assets and corrective work orders and then build from there. However, it would most helpful if you take the time to define objectives and goals and what functionality you would/should implement in the initial phase of your project and then phase it. This will pave the way for determine how each module should be configured to facilitate adding modules later.

Should we implement everything at once or should we do it by phases?

We passionately believe in crawl, walk, run. However, defining a long-term vision for an asset management program will provide direction and help determine the implementation sequence.

What if we don’t have a system today?

You probably have something, maybe Microsoft excel. But if this is the case, the main challenge is collecting your asset data. We have some pre-defined data templates built for the electrical/power generation industry for gas/diesel turbines, steam turbines, low-speed diesel engines, hydro-electrical plants and wind farms.

What if we have a system now?

This system becomes our primary source of master data for assets, preventive maintenance schedules, parts, suppliers, etc.

What is the project scope?

How is it documented? Together we define and align the project scope. It is part of the initial proposal and is the base for then estimate. Once the project officially begins, we dig deep into the scope during the design sessions and document everything going into Octave Attune EAM in the Design Document.

Can I change the scope once we have begun the implementation process? How do we change the scope?

These things happen. We just need to control them. This is documented and approved in a Change Order

Does it make sense to change the scope?

The only constant in life is change. But when it comes to implementing Octave Attune EAM, VisualK is extremely strict and we put a lot of time and effort in the initial phase of the project designing and documenting the scope. A justified change may be required. Someone saying at the end of the project “I thought the system would do this….” is a failure.

What is a change order?

It is a document which describes the nature and justification for the change, its impact on the implementation in terms of additional/less time and/or cost.

Who authorizes a change order?

It requires the signature of both the customer and VisualK’s project managers.

Do I need consulting services to implement?

Not necessarily. Can we do it by ourselves? Not necessarily. You need training and you would benefit from having a guide to navigate the implementation process.

Can we implement after just going through training?

You can. However, there is no training in world that would give you the knowledge that comes with years of experience. You should consider consulting services as part of your budget.

What is the process for implementing?

We have a methodology to guide this process, but in a nutshell, it works like this. We start by defining and design exactly how the system will work for you including work processes, metrics and reports. Then you configure the system in a test environment where you train and test to ensure that the system complies with the design. When you determine that the system and the users are ready, you setup a new environment and begin using the system in your day-to-day operations.

Where is the implementation work done?

Remotely versus onsite? How do I know the labor time reported is right? How do I know that we are being charged correctly? Before COVID-19 80% of the work was done remotely in one of our offices in San Juan, Guatemala, El Salvador or Atlanta. We used to visit customers to conduct design sessions, training and provide onsite support during a go-live.

As of March of 2020, during the COVID-19 pandemic, we have begun new projects and have been conducting all activities remotely may be done in a house in San Juan, Guatemala, El Salvador, Miami or Atlanta. Our consultants report their daily hours for a project and these are validated by the VisualK Project Manager. We submit detailed time sheets as supporting documentation for our invoices. However, the most important factor is TRUST. We understand that trust is hard to earn. And extremely easy to lose.

What is an engagement manager?

The engagement manager is senior member of our team that manages the relation with the customer and drives the discussions with senior management to understand the vision, strategy and objectives of implementing Octave Attune EAM. He is the ultimate responsible for the success of the project. Why should we use the engagement manager? There are soft and hard skills in an implementation project and the team. The engagement manager brings the experience and soft skills to the high-level conversations and translates that for the rest of the team.

Who needs to work in the implementation from our side?

Who are the key-users? What is the role of a key-user before, during and after an implementation? The key-users (also known as Core members) are experts or are familiar with the business area that the system covers along with the terminology and practices. They support the definition of Project scope including the examination of your business and define what Octave Attune EAM should do.

Work with your staff, management, and technical support staff and obtains information by conducting interviews, working sessions, and site visits. Provide in-depth knowledge of the business and assumes responsibility for design decisions, execution of system setup, and validation that design meets the business needs of the organization.

How much time/effort should they spend?

These are the people/roles that participate in a typical project and a ballpark estimate of the time that they need to invest:

  • Project Sponsor. 4hrs per month
  • Project Manager. 16 hrs/month
  • Key-User (Core Team Member). 10 hrs/week

Do we need a project manager from our company?

Yes. Your team would need to work hand in hand with our consultants and the company project manager will coordinate the internal activities and ensure that people deliver, and plans are met. What is the role of the consulting services project manager? To coordinate our consultants, ensure that the project is delivered on-time, withing budget and to your satisfaction.

Who makes the best project manager?

An IT or functional person? In our experience, a functional person can do a better job. However, either an IT or functional person with project management experience and/or certification should be considered.

What is the role of IT during the Implementation?

IT plays a support role. It is most important to understand that implementing Octave Attune EAM is NOT an IT project. It is an Operations and Maintenance project which could be supported by IT. There are some organizations, where IT are the experts at implementing systems and they can lead. To our friends in Operations and Maintenance, don’t walk away from the project because IT may be leading it.

Do I need to have a programmer in-house?

What would be the typical things that require a programmer? You don’t. If some integration is required, having a programmer around could help.

Can I make my own reports?

What tools are available to produce our own reports? Yes you can. Octave Attune EAM has a module called Advanced Reports which is based on IBM’s Cognos, that allows a user, with SQL experience, to edit standard reports or create new reports. If on-premise you can use other reporting tools, such as Crystal Reports, to generate reports outside of Octave Attune EAM.

Do I need to have a PMO?

Do we need to have a certified Project Manager? You don’t absolutely have to, BUT IT REALLY HELPS. More organizations realize the value of having these professionals in their roster.

Is there a methodology for implementing?

Yes. Are there different methodologies? We use 2; Infor Deployment Method (sort of traditional waterfall process) and the newest which is called Agility. Agility is based on the principle that Octave Attune EAM is pre-configured for your industry and, by design, meets 60% of your requirements. 30% requires some additional configuration and would include things like integrations to other systems and 10% is unique to your business/industry.

Which one should I use? The first criteria is whether there is a pre-configured solution for your industry. The second is if your business/industry conforms to the 60/30/10 guide.

What if we have our own methodology?

We will evaluate it and if it makes sense, we can work with it.

What is a design session?

This is a workshop conducted by our consultants with your key-users to discuss the processes and requirements for the implementation.

What is a design document?

This is the blueprint for the project. We put the specific details of which modules will be implemented and how exactly these modules will be configured. It also describes the workflows, controls and metrics that will be implemented. Who is responsible for creating a design document? VisualK is the ultimate responsible for drafting the document. We review it as a team. You decide what stays and what is taken way.

What is key-user training?

Once the test environment has been configured, our consultants train the team members responsible for testing the system.

What is a User Acceptance Test (UAT)?

These tests are performed by the key-users and the objective is to validate that the system has been built as per the design.

What is a development environment?

This is a copy of the Octave Attune EAM where we configure, develop, test and then test some more. It also serves the purpose of training environment. Think of it as a staging area.

What is a production environment?

This is where, once deployed, users go on a day-to-day to transact. It only contains the final, approved version of the configuration, metrics and reports.

Why everything is done in a development environment and then done again in a production environment?

The production environment must be a “clean” environment with only real transactions. Development, testing and fine-tuning will introduce a lot of transactions that you don’t want in your reports, right?

What documentation is produced during the implementation?

Here’s the laundry list:

  • Statement of Work (SOW) and other contracts
  • Design Document
  • Project Implementation Plan (MS Project)
  • Change Orders
  • Charter and Scope
  • Weekly Project Status Report
  • Risk Register
  • Cutover plan
  • Closing report.

Which meetings do you have during the implementation?

We are not big fans of meetings (for the sake of meetings). Over the life of the project we typically meet for these activities:

  • Design sessions
  • Design review sessions
  • Weekly status review (customer and VisualK project managers)
  • Key-user training
  • User acceptance test sessions
  • Readiness assessment
  • Post-implementation audit and review
  • Closing report review

What is a status report?

It is a 2-page report of the condition of project which includes milestones, overall progress, indicators, completed tasks and tasks for the next week. Here’s a sample

How is the data transferred from my current system to EAM?

We provide you standard templates, in MS Excel format. You would extract this data from your current system and we have tools to import the data into Octave Attune EAM

How do you load the master data into Octave Attune EAM?

Octave Attune EAM has a data import utility tool.

Do we have to validate the data that is loaded into EAM?

Yes! You’re the experts when it comes to your data, but most importantly this can be an opportunity to clean and update the data. You may have obsolete assets and parts which you don’t want in the new Octave Attune EAM.

What happens when is time to begin using the system for real (production)?

Let’s start by defining readiness first. The production system has been configured, all the users have received training and are proficient in the new tools, the cutover has been completed. So now comes day 1 and people just go about their business with the new tools implemented in Octave Attune EAM. We are typically on-site to support the users.

Do you do a parallel? What is a parallel?

A parallel is/was a methodology where the old system and the new system would co-exist and users would transact in the old system and then re-create the transaction in the new system. After a pre-defined period, both systems were compared, and they should have the same data and the numbers would match. VisualK DOES NOT do parallels. Because, users (“in their daily rush”) would enter the transaction in their old, familiar system and put the transaction away in a pile for whenever they get the time to enter it into the new system. This is a recipe for disaster.

What happens if the system does not work as intended?

You would never find this in production. It is the responsibility of the key-users, during the User Acceptance Test to guarantee that Octave Attune EAM is READY for primetime.

How do we go back?

There is no going back. We have checkpoints along the way: Proposal, Design Document, User Acceptance Tests, Cutover, Audit and Closing.

What is a go-live?

This IS the day when Octave Attune EAM is used for the first time to transact and support the business.

How do you close a project?

Who decides that the project is over? A few weeks after the go-live we conduct an audit of the system to determine how the system is being used and if there any functional gaps. With this information we produce a closing report which is discussed to the customer. The customer will approve this report and that officially concludes the project. It is a joint decision between the two parties.

Major Functionalities in EAM for PowerGen

Major Functionalities in EAM for PowerGen

Enterprise Asset Management software has continued to evolve over time to better meet the needs of different industries.

Octave Attune EAM, formerly HxGN EAM and previously Infor EAM, has been part of that evolution—from software installed on individual computers to a platform with cloud, web-based, and mobile options. But which capabilities can help maintain assets within a power plant? The answer is extensive, so let’s take a brief look at several key areas: work requests and execution, inventory management, and purchasing.

Visual K has worked with customers with different requirements across these processes. While some examples below focus on power generation, others apply to electric utilities that also manage distribution networks and customer service requests.

How Work Begins Within EAM

Let’s start with how jobs begin within EAM. A typical situation is an operator creating a work request. Operators and technicians are familiar with the equipment they work with every day, so they are often the first to notice an unusual noise or recognize that an adjustment may be needed.

Work can also originate from inspection rounds. Operators complete checklists and identify conditions that do not meet expected parameters, creating a request for follow-up maintenance.

For electric utilities involved in distribution, another common scenario is receiving calls from customers reporting power outages, fallen poles, damaged cables, or other issues. These reports can be tracked within the system and managed against defined response targets, including temporary and permanent resolutions.

When several people report the same incident, their calls, emails, or in-person reports can be associated with the same work order to avoid creating duplicate jobs.

Once the work has been properly identified, it is time to schedule and execute it.

Work Orders: More Than a Task List

We could write an entire article about work orders because of the details they can include and the different purposes they serve across industries—and even across teams within the same company.

For some users, the priority is safety. For others, it is cost control, completion time, or customer satisfaction. A job may be as simple as changing a light bulb or as complex as installing new equipment, which can require several specialists to assemble and commission its components.

Projects add another layer, potentially bringing together multiple work orders and budgets.

In an electric utility environment, when a customer reports a power outage, the company needs to understand the situation and coordinate its response. The work management process can help track job progress, the parts and personnel assigned to each task, and feedback documented by field teams.

Mobile workflows can also support the collection of comments and supporting media, depending on the application and configuration in use.

Safety as Part of Work Preparation

Another important consideration is preparing a safe work environment and completing the required isolation procedures before each job.

Documenting the safety procedures followed by operators, technicians, and safety personnel can support internal reviews and audits. These records may also help the company assess how consistently its procedures are being followed.

The software supports documentation and traceability; it does not replace the organization’s safety procedures, training, or required authorizations.

Breaking Work Orders into Activities

As a practical rule, each work order needs activities that answer a basic question: “What is going to happen?”

An activity can describe a complete task, such as “Replace blown fuse,” including the work associated with it. Other companies may prefer a more detailed breakdown:

  1. Travel to and from the site.
  2. Assess the situation.
  3. Complete the required safety procedures.
  4. Replace the blown fuse.

Parts can be planned, reserved, and issued through work orders, with the corresponding transactions associated with specific activities.

For example, if an electrician is assigned to replace the fuse in activity four, the fuse should be associated with that activity—not with the crew’s travel time.

Labor time can also be recorded against individual activities, and different roles can be assigned to different stages of the job. External labor may be included as well, whether it is contracted at a fixed price or an hourly rate.

Safety personnel may participate in preparing the work area, while an electrician performs the replacement once the required conditions have been established. Activities can also include checklists and instructions, particularly for recurring tasks.

Managing Spare Parts and Storerooms

If your organization issues parts to work orders, employees, or equipment, it probably manages one or more storerooms.

Inventory records need to remain accurate so maintenance teams can check which parts are available and identify when additional materials are required. Physical inventory counts are one way to verify that recorded quantities match actual stock.

Where the selected mobile solution supports the workflow, storeroom personnel can use mobile devices to record counts and submit adjustments. The timing of those updates depends on connectivity and synchronization.

Parts can also have minimum and maximum stock levels or reorder points defined by storeroom. These settings help guide replenishment decisions.

But what happens when you need parts or services that fall outside the usual replenishment process? That is where procurement workflows come in.

Connecting Maintenance with Purchasing

Authorized users can create requisitions for parts and services to begin the purchasing process.

Once a requisition has been approved, it can be converted into a purchase order. Separate suppliers generally require separate purchase orders, while an individual purchase order may include several parts or services and consolidate requirements from multiple requisitions.

Approval limits can be established so that users have different levels of purchasing authority.

Status workflows can also define who needs to review a purchase order and at which stage before final approval. These controls support internal policies requiring several people to review or authorize an expense.

Materials and services are then received and verified, and the relevant invoice records can be processed. The responsibilities for accounting and payment should be defined according to the organization’s financial processes and any ERP integrations.

More Than Work Execution

As you can see, Octave Attune EAM covers much more than work execution. This overview only scratches the surface of how work management, safety documentation, inventory, and purchasing can connect within an asset management platform.

The right approach depends on your organization’s requirements. Some companies may need to connect several of these processes from the beginning; others may choose to start with a more focused scope.

Configuration, mobile workflows, and integrations should be evaluated against the way your teams work and the capabilities included in the proposed solution.

Would you like to see how these processes could apply to your operation? Contact Visual K to explore Octave Attune EAM and discuss your maintenance, inventory, and purchasing requirements.

Maintenance and Reliability

Maintenance and Reliability

Asset Maintenance: Supporting Customers on the Road to Reliability

Visual K and Octave Attune EAM for Asset Maintenance

In most work environments, it is common to find a maintenance department. Whether responsible for facilities, machinery, computers, or office equipment, organizations continually look for ways to improve how their assets perform—helping them fail less often, last longer, and contribute more value to the business.

Visual K has been helping organizations across different industries track their maintenance activities and identify opportunities for improvement.

Founded in 1998 by Rene Nazario, Visual K designs solutions around customer needs and policies. Our team supports customers throughout the implementation process, from solution design to go-live and ongoing support. We also help teams develop the knowledge needed to use their tools effectively.

Octave Attune EAM, formerly HxGN EAM and previously Infor EAM, is part of that approach to enterprise asset management. Together with implementation services and the appropriate integrations, it helps connect asset information with maintenance processes.

The Road to Reliability Starts with Reactive Maintenance

When it comes to maintenance, organizations often recognize several stages along what we can call the “road to reliability.” As companies gain experience, their asset management practices develop as well.

The first response seems obvious: when a machine breaks, you fix it. However, when this becomes the main maintenance strategy, technicians can spend much of their time responding to breakdowns. Just as one machine is repaired, another important asset may fail—sometimes at the most critical moment.

This approach is commonly called reactive maintenance, with technicians frequently “putting out fires.”

Many companies establish a process for reporting breakdowns through work requests in their EAM system. This provides a way to document a problem and initiate the maintenance response.

Unexpected failures will not disappear entirely. However, organizations can take steps to reduce their dependence on emergency repairs.

Did you change the oil? Did you check the fuses? Are fluid levels correct? Are pressure and temperature readings within the expected operating range?

These are some of the questions that begin to emerge as an organization develops a preventive maintenance approach.

Building Preventive Maintenance Habits

Preventive maintenance involves scheduling activities before a failure occurs, using equipment documentation, operating requirements, and maintenance experience to determine what needs to be done and when.

A familiar example is changing the oil in a vehicle at specified time or mileage intervals. The work is performed even when the vehicle appears to be operating normally.

The same principle applies to industrial assets. Manufacturers may recommend inspections, lubrication, adjustments, and component replacements that cannot be justified by visual appearance alone.

As maintenance teams become more familiar with their equipment, they also identify patterns related to operating hours, cycle counts, usage frequency, or other measurements specific to each machine.

These observations can help refine preventive maintenance schedules and identify additional tasks. Any changes to manufacturer recommendations should be evaluated carefully against the asset’s operating conditions and technical requirements.

Experienced technicians play an important role in this process. Their observations, combined with documented maintenance history, help turn individual knowledge into information the wider team can use.

Moving Toward Condition-Based Maintenance

Another approach is condition-based maintenance, where maintenance decisions respond to the observed condition of an asset.

Monitoring systems can alert personnel when readings move outside defined parameters. In the original example, a facility monitors atmospheric CO₂ levels and activates alarms when a threshold is exceeded.

The immediate safety response must follow the facility’s established procedures and protective systems. EAM can support the maintenance follow-up by recording the event and organizing the work needed to investigate or address the issue.

With the appropriate integration and configuration, a condition trigger can initiate a work order and capture the time of the reading.

Rather than creating an empty work order, the workflow can use a predefined template with a description such as “Atmospheric Gas Level Exceeded—CO₂,” together with relevant activities, checklists, and instructions.

Different conditions can be associated with different responses. The objective is to connect the information captured by monitoring systems with a structured maintenance process.

Using Data to Support Predictive Maintenance

Predictive maintenance builds on the use of equipment data to identify patterns that may indicate developing problems.

Historical measurements, operating behavior, maintenance records, and current conditions can help teams assess the likelihood of a failure or identify when further investigation is needed.

Artificial intelligence and other analytical methods may support this process. However, predictive maintenance does not mean knowing with certainty exactly when a machine will fail. Its usefulness depends on the quality and relevance of the data, the analytical approach, and the ability to act on the findings.

Operating context matters, too.

For example, one of Visual K’s customers operated a power plant in the Caribbean, close to the shoreline. The customer found that the equipment required a more demanding maintenance approach than initially expected because local environmental conditions differed from those assumed in the original maintenance recommendations.

That experience illustrates why maintenance decisions should consider not only equipment specifications but also the environment in which the assets operate.

AI and the Internet of Things (IoT) can raise questions about cost, integration, and organizational change. A practical approach is to begin with a clearly defined maintenance problem and determine what information and capabilities are needed to address it.

Potential benefits include fewer unexpected interruptions, better-informed maintenance decisions, and improved use of asset life.

Supporting Reliability at Every Stage

No matter where your organization is on the road to reliability, asset management software can help bring greater structure to maintenance information and activities.

Reactive, preventive, condition-based, and predictive approaches do not have to be mutually exclusive. The appropriate combination depends on the assets involved, their operating context, and the consequences of failure.

A computerized maintenance management system (CMMS) or enterprise asset management (EAM) platform can help teams document failures, organize maintenance work, and track associated costs. Connections with ERP, monitoring, and other business systems can further support the flow of information.

Visual K has worked with customers using EAM alongside other solutions to reduce duplicate data entry and support documentation and reporting requirements.

With Octave Attune EAM, the objective remains the same: give teams useful information and organized processes to support their maintenance and reliability goals.

Contact Visual K to explore how Octave Attune EAM could support your organization’s next steps on the road to reliability.